What are my
goals for Year 6?
-
To implement the modified improvement plan, collect
data, and analyze data
How can I
achieve these goals?
-
You will put your revised improvement plan into
action, then collect and analyze the resultant data
in the same way you did for the original improvement
plan.
-
If you are satisfied with your results and feel
that you cannot improve more, you can skip to
the Year 10 instructions (prepare final report,
maintain gains of the project, and begin another
quality improvement project).
-
If you feel there is opportunity to improve
outcomes further or to refine your processes,
then there is nothing more to do this year.
Start the Year 7 instructions at the appropriate
time.
What will I need
to attest to in the ABR Personal Data Base for Year 6?
-
See below. Answers in bold would be correct based on
competing the RadiologyQuality.com recommendations.
-------------------------------------------
-------------------------------------------
Which of the following describes your progress this year
with regard to your current PQI project? (Please check
all that you have accomplished during this year)
__
I have not yet begun a PQI activity
__
I have chosen an appropriate project
__
I have made baseline measurements to document the
scope of the problem
__
I have analyzed the root cause of the problem
__
I have developed an action plan for improvement
__
I have instituted the action plan
__
I have made measurements to determine if
improvement has occurred
__
I have completed a PQI project, and am in the
process of choosing another
-------------------------------------------
-------------------------------------------
What does
RadiologyQuality.com recommend to fulfill these
requirements?
-
If you have chosen to design your own project or use
an existing external project, then click here for
general tips on analyzing data (OR)
-
If you have chosen a
RadiologyQuality.com
project, then click below for the recommended
data analysis technique:
-
Critical Results Project
-
Procedural Pause Project
-
Communication Protocol Project
What else do I
need to do?
-
Every year you must to log on to the ABR Personal
Database and attest to your compliance.
https://www.abronline.org/
-
You can document your compliance with us, if using a
RadiologyQuality.com project, in case you are
audited by the ABR.